CSL Thames Grounding: Not Enough ECDIS Training

 Accident, Accident report, ECDIS, grounding, maritime safety news  Comments Off on CSL Thames Grounding: Not Enough ECDIS Training
Mar 012012
 

View of ECDIS and position of bridge team

Lack of ECDIS-specific training, poorly placed bridge equipement and a master’s lack of support for an inexperienced third officer played key roles in the grounding of CSL Thames, a Maltese registered self-discharging bulk carrier, which grounded briefly in the Sound of Mull on  9 August 2011. An investigation report has now been published by the UK’s Marine Accident Investigation Branch.

At 1026 (UTC +1) on 9 August 2011, CSL Thames, a Maltese registered self-discharging bulk carrier, grounded briefly in the Sound of Mull while on passage from Glensanda to Wilhelmshaven. The vessel sustained bottom damage to her hull, including a 3-metre fracture to one of her water ballast deep tanks, which flooded. There were no reported injuries or pollution.

The MAIB investigation found that CSL Thames ran aground after the third officer had altered the vessel’s course to starboard of the planned track to avoid another vessel. He did not notice that the alteration would take CSL Thames into shallow water, and the audio alarm on the electronic chart display and information system (ECDIS) that should have alerted him to the impending danger was inoperative. Further, the master’s and other watchkeepers’ knowledge of the vessel’s ECDIS was insufficient and therefore no-one within the bridge team questioned the absence of the ECDIS audio alarm, or recognised that the system’s safety contour setting was inappropriate for the planned voyage.

Continue reading »